You have a project with the following tasks: Task A takes 40 hours and can start after the project starts. Task B takes 25 hours and should happen after the project starts. Task C must happen after Task A and takes 35 hours. Task D must happen after Tasks B and C and takes 30 hours. Task E must take place after Task C and takes 10 hours. Task F takes place after Task E and takes 22 hours. a. Draw the network diagram
b. What is the critical path and what is the length of the critical path?
c. If Task B actually takes 37 hours, what is the effect on the project?
d. What tasks must be completed before task D can begin?
e. If senior management tells you to complete the project 20 hours early, what is the project float? How can you meet this requirement? Does the critical path change?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 03:00
State 7 common key's for every keyboard
Answers: 1
question
Computers and Technology, 23.06.2019 13:00
Which one of the following voltages should never be measured directly with a vom? a. 1200 v b. 500 v c. 800 v d. 100v
Answers: 2
question
Computers and Technology, 24.06.2019 02:40
Has anyone seen my grandma shes been gone for 4 years already
Answers: 1
question
Computers and Technology, 24.06.2019 13:30
What is the most important for you to choose before you build a network?
Answers: 1
You know the right answer?
You have a project with the following tasks: Task A takes 40 hours and can start after the project s...
Questions
question
Biology, 13.08.2019 17:20
Questions on the website: 13722359