Given this hypothetical project with the following characteristics, answer the following questions: You are the project manager of a project to build crafty birdhouses.
You are to build three birdhouses a month for 6 months.
Each birdhouse is planned to cost $75.
Your project is scheduled to last for 6 months.
It is the beginning of month 3.
You have built 12 birdhouses and your CPI is 1.25

How is the project performing?
Please explain
Is it
Over budget and ahead of schedule
Under budget and ahead of schedule
Over budget and behind schedule
Under budget and behind schedule.

What is the actual cost of the project right now? (AC)

Assuming that the COST variance experienced so far in the project will continue, how much more money will it take to complete the project?(ETC)

If the variance experienced so far were to stop, what is the project's estimate at completion(EAC) ?

What is the project's TCPI using the project's budget at completion (TCPI = (BAC- EV)/(BAC - AC)) ?

Senior management wants to the percentage of the project that is complete. What should you report?((EV/BAC)*100%)

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 13:00
Which part of the cpu accepts data?
Answers: 1
question
Computers and Technology, 22.06.2019 16:20
It policy compliance and emerging technologies respond to the following: propose at least three control measures that organizations need to put in place to ensure that they remain complaint with emerging technologies and in a continually changing it environment. examine the correlation of effective configuration management and change control procedures to remain compliant with emerging technologies and it security changes.
Answers: 2
question
Computers and Technology, 22.06.2019 23:30
What is the digital revolution and how did it change society? what are the benefits of digital media?
Answers: 1
question
Computers and Technology, 23.06.2019 00:00
Which is the correct sequence of steps to set up a document in landscape orientation? a. select page setup from the file menu. then click the margins tab and select landscape. b. select page setup from the edit menu. then click the margins tab and select landscape. c. select page setup from the insert menu. then click the margins tab and select landscape. d. select page setup from the format menu. then click the margins tab and select landscape
Answers: 1
You know the right answer?
Given this hypothetical project with the following characteristics, answer the following questions:...
Questions
question
Mathematics, 03.02.2021 19:00
question
History, 03.02.2021 19:00
question
Mathematics, 03.02.2021 19:00
question
Mathematics, 03.02.2021 19:00
Questions on the website: 13722363