subject
Engineering, 23.08.2019 02:30 laidbackkiddo412

Awave soldering machine failures follow 3-parameter weibull distribution with β = 1.6, η = 800 hours and γ = 500 hours. the cost of one pm is $ 6000 and the cost of an unexpected failure is $ 16 000. the machine operates 24 hours/day and pms are done every three months. determine the yearly cost for this maintenance schedule.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Steel is coated with a thin layer of ceramic to protect against corrosion. what do you expect to happen to the coating when the temperature of the steel is increased significantly? explain.
Answers: 1
question
Engineering, 04.07.2019 18:10
You are making beer. the first step is filling the glass carboy with the liquid wort. the internal diameter of the carboy is 15 in., and you wish to fill it up to a depth of 2 ft. if your wort is drawn from the kettle using a siphon process that flows at 3 gpm, how long will it take to fill?
Answers: 1
question
Engineering, 04.07.2019 18:10
Ahot wire operates at a temperature of 200°c while the air temperature is 20°c. the hot wire element is a tungsten wire of 5 um diameter and 2 mm in length. plot using excel current, heat transfer and heat generated by the wire for air velocity varying from 1-10 m/s in steps of lm/s? matlab the sensor voltage output, resistance, or assume nu 0.989 re033pr13 take air properties at tr (200°c20°c)/2 = 110°c properties of tungsten: c 0.13 kj/kg.k 3 p 19250 kg/m k (thermal conductivity) = 174 w/m.k
Answers: 2
question
Engineering, 04.07.2019 18:10
The flow rate of air through a through a pipe is 0.02 m5/s. a pitot static tube is placed in the flow. the radius of the pitot static tube is 1 mm. assuming the flow to be steady and the air to be at 300k, calculate the difference in total and static pressure if the diameter of the pipe is: (a) d 0.1 m d 0.05 m (c) d 0.01 m
Answers: 2
You know the right answer?
Awave soldering machine failures follow 3-parameter weibull distribution with β = 1.6, η = 800 hours...
Questions
question
Engineering, 11.10.2020 23:01
question
English, 11.10.2020 23:01
question
Mathematics, 11.10.2020 23:01
question
Mathematics, 11.10.2020 23:01
Questions on the website: 13722363