Engineering, 07.09.2019 03:20 iibabycarrotsii

A7-station transfer line has been observed over a 40-hour period. the process times at each station are as follows: station 1, 0.80 min; station 2, 1.10 min; station 3, 1.15 min; station 4, 0.95 min; station 5, 1.06 min; station 6, 0.92 min; and station 7, 0.80 min. the transfer time between stations = 6 sec. the number of downtime occurrences = 110, and hours of downtime = 14.5 hours. a proposal has been submitted to locate a storage buffer (capacity = 20) between stations 4 and 5 to improve line efficiency. using the upper-bound approach, compute the line efficiency and production rate of the new buffer installed transfer line.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
If a particle moves along a path such that r : (3 sin t) m and ? : 2t rad, where t is in seconds. what is the particle's acceleration in m/s in 4 seconds? a)- 16.43 b)- 16.29 c)- 15.21 d)- 13.79
Answers: 1
question
Engineering, 04.07.2019 18:10
Carbon dioxide gas expands isotherm a turbine from 1 mpa, 500 k at 200 kpa. assuming the ideal gas model and neglecting the kinetic and potential energies, determine the change in entropy, heat transfer and work for each kilogram of co2.
Answers: 2
question
Engineering, 04.07.2019 18:20
Air flows over a heated plate àt a velocity of 50m/s. the local skin factor coefficient at a point on a plate is 0.004. estimate the local heat transfer coefficient at this point.the following property data for air are given: density = 0.88kg/m3 , viscosity 2.286 x 10 ^-5 kgm/s , k = 0.035w/mk ,cp = 1.001kj/kgk. use colburn reynolds analogy.
Answers: 1
question
Engineering, 04.07.2019 18:20
Modern high speed trains do not have perpendicular expansion gaps where rails are joined end-to-end any more they are mostly welded together but what might happen if there was a spell of particularly hot weather that causes inspection of the tracks?
Answers: 1
You know the right answer?
A7-station transfer line has been observed over a 40-hour period. the process times at each station...
Questions
question
Mathematics, 07.10.2019 17:10
question
Mathematics, 07.10.2019 17:20
question
History, 07.10.2019 17:20
Questions on the website: 13722360