Acomposite floor system consists of w18 x 97 beams and a 5-inch-thick reinforced concrete
floor slab. the span length is 30 feet, and the beams are spaced at 8 feet. in addition to the
weight of the slab, there is a construction load of 20 psf. a uniform live load of 800 psf is
expected during the life of the floor. assume that there is no support during the construction
phase. a992 steel is used, and normal weight concrete is used (we = 145 ). the 28-day
compressive strength of concrete is f' = 4 ksi.
a) compute the total stress at the bottom of steel and the stress at the top of concrete.
b) determine the flexural strength of the composite section.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 03.07.2019 23:20
Two technicians are discussing the intake air temperature (iat) sensor. technician a says that the computer uses the iat sensor as a backup to the engine coolant temperature (ect) sensor. technician b says that the powertrain control module (pcm) will subtract the calculated amount of fuel if the air measures hot. who is correct
Answers: 3
question
Engineering, 04.07.2019 18:10
Slip occurs via two partial dislocations because of (a) the shorter path of the partial dislocation lines; (b) the lower energy state through partial dislocations; (c) the charge balance.
Answers: 1
question
Engineering, 04.07.2019 18:20
For each of the following process: a) sketch the p-v diagram, b)sketch t-s diagram, c) sketch t-v diagram, d) sketch the boundary work on one of the diagrams (a, b or c) and e) sketch the reversible heat transfer on one of the diagrams (a, b or c): 1- isobaric process from compressed liquid to superheated vapor 2- isothermal process from compressed liquid to superheated vapor 3- isentropic process from compressed liquid to superheated vapor
Answers: 3
question
Engineering, 04.07.2019 19:10
For a process taking place in a closed system containing gas, the volume and pressure relationship is pvi-constant. -1.5 bar, the process starts with initial conditions, pi = =0.03 m3 and ends with final volume, v2-0.05 m3 determine the work done by the gas.
Answers: 2
You know the right answer?
Acomposite floor system consists of w18 x 97 beams and a 5-inch-thick reinforced concrete
floo...
Questions
question
Mathematics, 09.12.2020 18:00
question
Geography, 09.12.2020 18:00
Questions on the website: 13722362