Engineering, 23.11.2019 00:31 Vauzh

On average 16 new batches of parts are started through a certain plant each week. average batch quantity is 50 parts that are processed through a sequence of seven machines. setup time per machine per batch averages 4 hours, and average operation time per machine for each part is 12 min. nonoperation time per batch at each machine averages 8 hours. there are 37 machines in the factory. any machine can be set up for any type of batch processed in the plant. the plant operates 40 hours per week. the plant manager complains that almost 65 hours of overtime must be authorized each week to keep up with the production schedule. determine
(a) manufacturing lead time for an average order,
(b) weekly production capacity of the plant if all machines were operated at 100% utilization,
(c) current utilization of the plant, and
(d) average work-in-process (number of parts) in the plant.
(e) why must overtime be authorized to achieve the desired output?

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
If a particle moves along a path such that r : (3 sin t) m and ? : 2t rad, where t is in seconds. what is the particle's acceleration in m/s in 4 seconds? a)- 16.43 b)- 16.29 c)- 15.21 d)- 13.79
Answers: 1
question
Engineering, 04.07.2019 18:10
Aplate clutch has a single pair of mating friction surfaces 250-mm od by 175-mm id. the mean value of the coefficient of friction is 0.30, and the actuating force is 4 kn. a) find the maximum pressure and the torque capacity using the uniform-wear model. b) find the maximum pressure and the torque capacity using the uniform-pressure model.
Answers: 3
question
Engineering, 04.07.2019 18:20
Vibration monitoring this technique uses the noise or vibration created by mechanical equipment and in seme cases by plant systems to detemine their actual condtion. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 19:10
What are the major differences between injection molding and extrusion?
Answers: 2
You know the right answer?
On average 16 new batches of parts are started through a certain plant each week. average batch quan...
Questions
question
Mathematics, 14.09.2020 19:01
question
Chemistry, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Biology, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
English, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Social Studies, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
English, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
French, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Biology, 14.09.2020 19:01
question
Mathematics, 14.09.2020 19:01
question
Biology, 14.09.2020 19:01
Questions on the website: 13722360