Engineering, 14.02.2020 04:09 noahdavis58
During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective) parts and 17 defective parts were produced. The operation cycle consists of a processing time of 5.23 min, and a part handling time of 0.58 min. Every 50 parts, a tool change is performed, and this takes 4.2 min. The machine experienced several breakdowns during the week.
Determine
(a) hourly production rate of acceptable parts,
(b) scrap rate, and
(c) availability (proportion uptime) of the machine during this week.
Answers: 2
Engineering, 03.07.2019 14:10
Line joining liquid phase with liquid and solid phase mixture is known as: a) liquidus b) solidus c) tie line d) none of the mentioned
Answers: 2
Engineering, 03.07.2019 14:10
If the thermal strain developed in polyimide film during deposition is given as 0.0044. assume room temperature is kept at 17.3 c, and thermal coefficient of expansion for the film and the substrate are 54 x 10^-6c^-1 and 3.3 x 10^-6c^-1respectively. calculate the deposition temperature.
Answers: 3
Engineering, 04.07.2019 03:10
What precautions should you take to prevent injuries when dealing with heavy loads?
Answers: 1
Engineering, 04.07.2019 18:10
What difference(s) did you notice using a pneumatic circuit over hydraulic circuit.explain why the pneumatic piston stumbles when it hits an obstacle.
Answers: 2
During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective)...
History, 09.07.2019 10:20
Biology, 09.07.2019 10:20
History, 09.07.2019 10:20
English, 09.07.2019 10:20
Chemistry, 09.07.2019 10:20
Health, 09.07.2019 10:20
Mathematics, 09.07.2019 10:20
English, 09.07.2019 10:20
Mathematics, 09.07.2019 10:20
Chemistry, 09.07.2019 10:20
Mathematics, 09.07.2019 10:20
Mathematics, 09.07.2019 10:20
History, 09.07.2019 10:20