subject
Engineering, 14.06.2020 07:57 laywah4

1.Twenty machines are operated for 100 hours. One machine fails in 60 hours and another fails in 70 hours. What is the mean time between failures?

ansver
Answers: 1

Another question on Engineering

question
Engineering, 03.07.2019 23:20
Two technicians are discussing the intake air temperature (iat) sensor. technician a says that the computer uses the iat sensor as a backup to the engine coolant temperature (ect) sensor. technician b says that the powertrain control module (pcm) will subtract the calculated amount of fuel if the air measures hot. who is correct
Answers: 3
question
Engineering, 04.07.2019 18:10
Water at 70°f and streams enter the mixing chamber at the same mass flow rate, determine the temperature and the quality of the exiting stream. 0 psia is heated in a chamber by mixing it with saturated water vapor at 20 psia. if both streams enters the mixing chamber at the same mass flow rate, determine the temperature and the quality of the existing system.
Answers: 2
question
Engineering, 04.07.2019 18:10
Afluid flows with a velocity field given by v=(x/t)i.. determine the local and convective accelerations when x=3 and t=1.
Answers: 2
question
Engineering, 04.07.2019 18:20
Determine the damped natural frequencies and the steady state response of a decoupled damped forced two degrees of freedom system. 10ä1 + 2q1 20q1 10 cos t; 10q2 +4q2 + 40q2 10 cos t
Answers: 3
You know the right answer?
1.Twenty machines are operated for 100 hours. One machine fails in 60 hours and another fails in 70...
Questions
question
Mathematics, 14.05.2021 01:30
question
Mathematics, 14.05.2021 01:30
question
Mathematics, 14.05.2021 01:30
Questions on the website: 13722359