A heavy construction firm has been awarded a contract to build a large concrete dam. It is expected that a total of 8 years will be required to complete the work. The firm will buy $600,000 worth of special equipment for the job. During the preparation of the job cost estimate, the following utilization schedule was computed for the special equipment: Year Utilization (hr/yr)
1 6000
2 4000
3 4000
4 1600
5 800
6 800
7 2200
8 2200
At the end of the job, it is estimated that the equipment can be sold at auction for $60,000.
(a) Compute the sum-of-years-digits' depreciation schedule.
(b) Compute the unit-of-production depreciation schedule

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Give heat transfer applications for the following, (i) gas turbines (propulsion) ) gas turbines (power generation). (iii) steam turbines. (iv) combined heat and power (chp). (v) automotive engines
Answers: 1
question
Engineering, 04.07.2019 18:10
Consider a large isothermal enclosure that is maintained at a uniform temperature of 2000 k. calculate the emissive power of the radiation that emerges from a small aperture on the enclosure surface. what is the wavelength ? , below which 10% of the emission is concentrated? what is the wavelength ? 2 above which 10% of the emission is concentrated? determine the wavelength at which maximum spectral emissive power occurs. what is the irradiation incident on a small object placed inside the enclosure?
Answers: 2
question
Engineering, 04.07.2019 18:10
Shafts are machine elements that are used to a) carry axial loads b) direct shear loads c) transmit power d) rotate at constant speed e) none of the above circular and square shafts subjected to the same torque under the same circum behave a) the same way b) almost the same way
Answers: 2
question
Engineering, 04.07.2019 18:20
Asolid cylinder is concentric with a straight pipe. the cylinder is 0.5 m long and has an outside diameter of 8 cm. the pipe has an inside diameter of 8.5 cm. the annulus between the cylinder ad the pipe contains stationary oil. the oil has a specific gravity of 0.92 and a kinematic viscosity of 5.57 x 10-4 m2/s. most nearly, what is the force needed to move the cylinder along the pipe at a constant velocity of 1 m/s?
Answers: 3
You know the right answer?
A heavy construction firm has been awarded a contract to build a large concrete dam. It is expected...
Questions
question
History, 19.02.2021 21:20
question
Mathematics, 19.02.2021 21:20
question
Mathematics, 19.02.2021 21:20
Questions on the website: 13722360