Engineering, 21.09.2020 17:01 mathisfun568

A three-phase Y-A transformer is rated 225-kv: 24-kv, 400 MVA and has a single-phase equivalent series reactance of 6.08 Ω as referred to its high-voltage terminals. The transformer is supplying a load of 375 MVA at 0.89 power factor leading at a voltage of 24 kV (line to line) on its low-voltage side. It is supplied from a feeder whose impedance is 0.17 +/2.2 Ω connected to its high-voltage terminals. For these conditions; 3. i. draw the per-phase equivalent circuit diagram
ii. draw the per-phase phasor diagram
iii. calculate:
a. The line-to-line voltage at the high-voltage terminals of the transformer
b. The line-to-line voltage at the sending end of the feeder.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Apipe with an outside diameter of 15 cm is exposed to an ambient air and surrounding temperature of -20°c. the pipe has an outer surface temperature of 65°c and an emissivity of 0.85. if the rate of heat loss from the pipe surface is 0.95 kw per meter of length, the external convective heat transfer coefficient (h) is: (a) 12.5 w/m"k (b) 18.6 w/mk (c) 23.7 w/mk (d) 27.9 w/mk (e) 33.5 w/mk
Answers: 1
question
Engineering, 04.07.2019 18:20
Find the kinematic pressure of 160kpa. for air, r-287 j/ kg k. and hair al viscosity of air at a temperature of 50°c and an absolute (10 points) (b) find the dynamic viscosity of air at 110 °c. sutherland constant for air is 111k
Answers: 3
question
Engineering, 04.07.2019 18:20
An open feedwater heater operates at steady state with liquid entering at inlet 1 with t? = 40°c and pl = 1 .2 mpa. water vapor att2-200°c and p2 = 1.2 mpa enters at inlet 2. saturated liquid water exits with a pressure of pa 1.2 mpa. neglect heat transfer with the surroundings and all kinetic and potential energy effects, determine the mass flow rate of steam at inlet 2 if the mass flow rate of liquid water at inlet 1 is given as 2 kg/s.
Answers: 3
question
Engineering, 04.07.2019 19:10
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
A three-phase Y-A transformer is rated 225-kv: 24-kv, 400 MVA and has a single-phase equivalent seri...
Questions
Questions on the website: 13722361