The task of framing a building has been estimated to take anaverage of 25 days with astandard deviation of 4 days. What duration should be used if there is to be a 90%confidence that the duration will not be exceeded?

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Apump is used to circulate hot water in a home heating system. water enters the well-insulated pump operating at steady state at a rate of 0.42 gal/min. the inlet pressure and temperature are 14.7 lbf/in.2, and 180°f, respectively; at the exit the pressure is 60 lbf/in.2 the pump requires 1/15 hp of power input. water can be modeled as an incompressible substance with constant density of 60.58 lb/ft3 and constant specific heat of 1 btu/lb or. neglecting kinetic and potential energy effects, determine the temperature change, in °r, as the water flows through the pump.
Answers: 1
question
Engineering, 04.07.2019 18:10
Afluid flows with a velocity field given by v=(x/t)i.. determine the local and convective accelerations when x=3 and t=1.
Answers: 2
question
Engineering, 04.07.2019 18:10
Water at 55c flows across a flat plate whose surface temperature is held constant at 95c. if the temperature gradient at the plate's surface for a given value of x is 18 c/mm, find a) local heat transfer coefficient. b) heat flux
Answers: 3
question
Engineering, 04.07.2019 18:10
Burgers vector is generally parallel to the dislocation line. a)-true b)-false
Answers: 2
You know the right answer?
The task of framing a building has been estimated to take anaverage of 25 days with astandard deviat...
Questions
question
Mathematics, 13.11.2020 19:40
question
Mathematics, 13.11.2020 19:40
question
Mathematics, 13.11.2020 19:40
question
History, 13.11.2020 19:40
Questions on the website: 13722363