During variable control charting a trend of four consecutive points is noted on both the
average and range charts. The average chart is
increasing and the range chart is decreasing.
One may make which of the following
conclusions?
a. No conclusions may be made yet
b. The nominal measurement is increasing
c. The variability is decreasing
d. The process is improving

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The filament of an incandescent lamp has a temperature of 2000k. calculate the fraction of radiation emitted in the visible light band if the filament is approximated as blackbody
Answers: 2
question
Engineering, 04.07.2019 18:10
Items are similar to the free issue items, but their access is limited. (clo5) a)-bin stock items free issue b)-bin stock controlled issue c)-critical or insurance spares d)-rebuildable spares e)-consumables
Answers: 1
question
Engineering, 04.07.2019 18:10
Ifa component is made of two or more materials with different modulus of elasticity (e), it is called a composite member and we calculate the factor·n". mention the formula for calculating n". also, ifn> 1, explain what will happen to the 1. transformed.gi) ifn 1, what will happen to the material when transformed material when
Answers: 1
question
Engineering, 04.07.2019 18:20
Inspection for bearing condition will include: (clo4) a)-color b)-smell c)-size d)-none of the above
Answers: 1
You know the right answer?
During variable control charting a trend of four consecutive points is noted on both the
avera...
Questions
question
Mathematics, 28.05.2020 05:03
Questions on the website: 13722360