As a materials engineer in charge of designing concrete mix and facing the following problems, which admixture would you use in each case during mixing or at the
jobsite?
a. There is a large quantity of freshly mixed concrete and the work at the job-site
had to stop because of rain.
b. More time is expected to be needed for finishing concrete.
c. The structure is subjected to freezing
d. Concrete is to be around tightly spaced reinforcing steel.
e. Concrete mix will be hauled a long distance.
f. High early strength concrete is required, but not necessarily high ultimate
strength.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 03.07.2019 14:10
Explain the difference laminar and turbulent flow. explain it with the shear stress and the velocity profiles.
Answers: 1
question
Engineering, 03.07.2019 14:10
When at a point two solid phase changes to one solid phase on cooling then it is known as a) eutectoid point b) eutectic point c) peritectic point d) peritectoid point
Answers: 3
question
Engineering, 03.07.2019 14:10
Amass of 1.5 kg of air at 120 kpa and 24°c is contained in a gas-tight, frictionless piston-cylinder device. the air is now compressed to a final pressure of 720 kpa. during the process, heat is transferred from the air such that the temperature inside the cylinder remains constant. calculate the boundary work input during this process.
Answers: 2
question
Engineering, 04.07.2019 12:10
On a average work day more than work place firs are reorted
Answers: 1
You know the right answer?
As a materials engineer in charge of designing concrete mix and facing the following problems, whic...
Questions
question
Biology, 18.09.2019 11:30
Questions on the website: 13722367