Engineering, 01.03.2021 20:40 Attaullah8207

Wright Construction specializes in the construction of communications towers for various cell carriers. On one of the company’s recent projects, there was one fatality. Workers have reported several injuries since then. In light of this situation, the company is redoubling its efforts to prevent accidents, also known as industrial hygiene. Name three potentially fatal accidents that could occur during the construction of a communication tower and the corresponding health effects workers might experience (acute, chronic, local, or systemic). Also, identify the corresponding OSHA standard that would help the company prevent the accident from occurring, including any relevant personal protective equipment.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The temperature of air decreases as it is compressed by an adiabatic compressor. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:10
Condition monitoring is a major component of. (clo4) a)- predictive maintenance. b)-preventive maintenance c)-proactive maintenance d)-reactive maintenance.
Answers: 1
question
Engineering, 04.07.2019 18:10
Aturning operation is performed with following conditions: rake angle of 12°, a feed of 0.35 mm/rev, and a depth of cut of 1.1 mm. the work piece is aluminum alloy 6061 with t6 heat treatment (a16061-t6). the resultant chip thickness was measured to be 1.0 mm. estimate the cutting force, fc. use shear stress of 207 mpa and coefficient of friction on the tool face of 0.6.
Answers: 1
question
Engineering, 04.07.2019 19:10
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
Wright Construction specializes in the construction of communications towers for various cell carrie...
Questions
question
Mathematics, 30.09.2019 03:00
question
History, 30.09.2019 03:00
question
World Languages, 30.09.2019 03:00
Questions on the website: 13722363