Disk Scheduling (45 Points). Assume that you are trying to schedule track requests for the arm on a disk with 150 tracks. Currently the following set of disk requests exists in a queue (order that requests were received): 66, 138, 93, 77, 79, 24, 5. The disk arm can move at the rate of 1 track per time unit. As these requests are being processed, four more requests come in at the following times: 111 at t=20, 14 at t=50, 102 at t=75, and 22 at t=100. Using the simulation format and scheduling policies we covered in class, complete the following the problems: Assuming that the disk arm is currently positioned over track 49, use the Shortest Seek Time First (SSFT) Scheduler to indicate the order in which the track requests are processed, and the total amount of time that it takes to process the entire set.
Assuming that the disk arm is currently positioned over track 49 and is traveling in the direction of increasing track numbers, use the Circular Scan (C-SCAN) Scheduler to indicate the order in which the track requests are processed, and the total amount of time that it takes to process the entire set. Assume that the quick return from the end of the disk to the beginning takes 5 time units.
Assuming that the disk arm is currently positioned over track 49 and is traveling in the direction of increasing track numbers, use the LOOK Scheduler to indicate the order in which the track requests are processed, and the total amount of time that it takes to process the entire set.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Thermal stresses are developed in a metal when its a) initial temperature is changed b) final temperature is changed c) density is changed d) thermal deformation is prevented e) expansion is prevented f) contraction is prevented
Answers: 2
question
Engineering, 04.07.2019 18:10
Assuming compressible flow of air and that the measurements are done at flagstaff a pitot static tube that gives the difference of total and static pressure measures 0.35 m of mercury. what is the velocity of air? assume the temperature to be 300k. (submit your excel or matlab calculation sheet)
Answers: 1
question
Engineering, 04.07.2019 18:20
Derive the correction factor formula for conical nozzle i=-(1+ cosa) and calculate the nozzle angle correction factor for a nozzle whose divergence hal-fangle is 13 (hint: assume that all the mass flow originates at the apex of the cone.
Answers: 3
question
Engineering, 04.07.2019 19:10
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
Disk Scheduling (45 Points). Assume that you are trying to schedule track requests for the arm on a...
Questions
question
Mathematics, 18.09.2019 15:30
question
English, 18.09.2019 15:30
question
Chemistry, 18.09.2019 15:30
question
Mathematics, 18.09.2019 15:30
Questions on the website: 13722367