A water district wishes to compare alternative plans for additional water supplies, using a forty-year period of analysis and an interest rate of 6%.
 A gravity plan would require an investment of $5,000,000 for construction and
$20,000 per year for operation and maintenance.
 A pumping plan would require $3,000,000 for initial construction, an additional
investment of $500,000 in the tenth year, and $50,000 per year for operation
and maintenance. The pumping plan would also incur power costs of $100,000
per year for the first ten years and after connection to another source of demand
additional power costs of $100,000 per year.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Fluids at rest possess no flow energy. a)- true b)- false
Answers: 3
question
Engineering, 04.07.2019 18:10
The higher the astm grain-size number, the coarser the grain is. a)-true b)-false
Answers: 3
question
Engineering, 04.07.2019 18:10
Atmospheric air has a temperature (dry bulb) of 80° f and a wet bulb temperature of 60° f when the barometric pressure is 14.696 psia. determine the specific humidity, grains/lb dry air. a. 11.4 c. 55.8 d. 22.5 b. 44.1
Answers: 1
question
Engineering, 04.07.2019 18:20
Asolid cylinder is concentric with a straight pipe. the cylinder is 0.5 m long and has an outside diameter of 8 cm. the pipe has an inside diameter of 8.5 cm. the annulus between the cylinder ad the pipe contains stationary oil. the oil has a specific gravity of 0.92 and a kinematic viscosity of 5.57 x 10-4 m2/s. most nearly, what is the force needed to move the cylinder along the pipe at a constant velocity of 1 m/s?
Answers: 3
You know the right answer?
A water district wishes to compare alternative plans for additional water supplies, using a forty-y...
Questions
Questions on the website: 13722362