A concrete dam is 32m long from the upstream side to the downstream end. The dam is situated on an 18 m thick stratum of soil that has a coefficient of permeability equal to 0.5 m per day. Firm, hard clay and rock lie underlie the described soil stratum. The base of the dam is installed at a level 2 m below the natural soil surface. Required:
Draw the flownet for seepage occurring beneath the dam, and compute seepage in cubic meter per day per meter of dam width (perpendicular to the paper) for the conditions where the reservoir water against the upstream face of the dam is 20m above the soil surface and water level at the downstream end is at 2m above the soil surface.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 08:10
Which of the following is an easy way to remember the modified “x” tire rotation? a. nondrive wheels straight, cross the drive wheels b. drive wheels straight, cross the nondrive wheels c. drive wheels crossed, nondrive wheels straight d. drive wheels crossed, nondrive wheels crossed
Answers: 1
question
Engineering, 04.07.2019 18:10
Aplate clutch has a single pair of mating friction surfaces 250-mm od by 175-mm id. the mean value of the coefficient of friction is 0.30, and the actuating force is 4 kn. a) find the maximum pressure and the torque capacity using the uniform-wear model. b) find the maximum pressure and the torque capacity using the uniform-pressure model.
Answers: 3
question
Engineering, 04.07.2019 18:10
Water in a partially filled large tank is to be supplied to the roof top, which is 8 m above the water level in the tank, through a 2.2-cm-internal-diameter pipe by maintaining a constant air pressure of 300 kpa (gage) in the tank. if the head loss in the piping is 2 m of water, determine the discharge rate of the supply of water to the roof top in liters per second.
Answers: 3
question
Engineering, 04.07.2019 18:20
How much power could a wind turbine produce if it had the following specifications? cp = 0.45 -d=1.2kg/m3 d=50m v 5m/s
Answers: 2
You know the right answer?
A concrete dam is 32m long from the upstream side to the downstream end. The dam is situated on an 1...
Questions
question
Mathematics, 18.10.2020 01:01
Questions on the website: 13722367