Multiple Response: Which of the following are the most
commonly found issues with CPM scheduling, or the Critical
Path Method?
A) A CPM schedule is built before the overall cost of the project is determined and therefore projects are hurried near completion in order to stay under budget

B) An inaccurate prediction of the duration of project activities and tasks

C) A lack in ability to absorb delays

D) A failure to take into account the finite amount of resources available throughout the job

ansver
Answers: 2

Another question on Geography

question
Geography, 24.06.2019 03:30
Using plate tectonics and elastic rebound theory, describe why juan de fuca plate subduction produces so few earthquakes. what will happen in the future?
Answers: 1
question
Geography, 24.06.2019 12:30
Which australian state leads the nation in the production of dairy products? a. western australia b. northern territory c. queensland d. victoria
Answers: 1
question
Geography, 24.06.2019 18:30
Using examples from various part of the world that is countries, examine the assertion that mere presence of abundant natural resources in a country does not guarantee rapid socio economic development?
Answers: 3
question
Geography, 24.06.2019 23:00
All of the following are possible solutions that may be used to address agricultural issues in the future except decrease biodiversitydecrease pesticide usedevelop "cleaner" pesticidesincrease organic farming
Answers: 1
You know the right answer?
Multiple Response: Which of the following are the most
commonly found issues with CPM schedulin...
Questions
Questions on the website: 13722361