According to the document shown, why might slippage occur when you manage a project using a CPM diagram?

A. The relationship between tasks is unclear.

B. The path contains no slack time.

C. The diagram includes only the most critical tasks.

D. The duration of each task is expressed in days.

E. The estimation of resources needed for each task is less accurate.

ansver
Answers: 3

Another question on Health

question
Health, 22.06.2019 15:50
Does the weight loss program have practical significance? a. no, the program is not practically significant because the results are likely to occur even if the weight loss program has no effect. b. yes, the program is practically significant because the results are too unlikely to occur by chance. c. yes, the program is practically significant because the amount of lost weight is large enough to be considered practically significant. d. no, the program is not practically significant because the amount of weight lost is trivial.
Answers: 2
question
Health, 22.06.2019 21:30
Which of the following statements is true about body composition? a. body composition is the percentage of fat to lean body mass. b. body composition is a measure of one's body weight. c. body composition is a measure of one's essential body fat. d. body composition is not a good indicator of overall health. select the best answer from the choices provided. a
Answers: 1
question
Health, 22.06.2019 22:00
Um yea this might be weird to say up here but me and my girl got freaky and shoved a bottle up my but thole and now is stuck. so what do i do?
Answers: 1
question
Health, 23.06.2019 01:30
Which method will provide the most emotional support in a new exercise program
Answers: 2
You know the right answer?
According to the document shown, why might slippage occur when you manage a project using a CPM diag...
Questions
question
Business, 04.02.2021 05:30
Questions on the website: 13722362