Mathematics, 15.07.2019 11:30 jadenmenlovep7s7uj

Aperson-hour is a unit of measure representing one person working for one hour. a construction foreman estimates that it will take 2880 person-hours to build a new library. if 12 workers are scheduled to work on the project at the same time how many hours will it take to complete the project?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:20
Ab and bc form a right angle at point b. if a= (-3,-1) and b= (4,4) what is the equation of bc?
Answers: 1
question
Mathematics, 21.06.2019 20:30
What is always true about a positive integer raised to a negative odd power?
Answers: 1
question
Mathematics, 21.06.2019 21:00
Yahir designs bracelets. he uses between 9 and 15 red and yellow beads in the ratio of 2 red bead to 5 yellow beads. drag the beads into the container to meet these requirements
Answers: 2
question
Mathematics, 21.06.2019 23:30
How do you find the distance of each number from the mean
Answers: 1
You know the right answer?
Aperson-hour is a unit of measure representing one person working for one hour. a construction forem...
Questions
Questions on the website: 13722360