Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Your client has saved $1,860 for a down payment on a house. a government loan program requires a down payment equal to 3% of the loan amount. what is the largest loan amount that your client could receive with this program
Answers: 3
question
Mathematics, 21.06.2019 19:30
Needmax recorded the heights of 500 male humans. he found that the heights were normally distributed around a mean of 177 centimeters. which statements about max’s data must be true? a) the median of max’s data is 250 b) more than half of the data points max recorded were 177 centimeters. c) a data point chosen at random is as likely to be above the mean as it is to be below the mean. d) every height within three standard deviations of the mean is equally likely to be chosen if a data point is selected at random.
Answers: 2
question
Mathematics, 21.06.2019 20:30
Find the solution(s) to the system of equations. select all that apply y=x^2-1 y=2x-2
Answers: 2
question
Mathematics, 21.06.2019 21:10
Hey free points ! people i have a few math questions on my profile consider looking at them i have to get done in 30 mins!
Answers: 1
You know the right answer?
Using pert, adam munson was able to determine that the expected project completion time for the cons...
Questions
question
Mathematics, 19.02.2020 21:24
Questions on the website: 13722367