In 18 days, 20 workers can build a school. how many days would it take if there were only 12 workers?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
Asmall business produces and sells balls. the fixed costs are $20 and each ball costs $4.32 to produce. each ball sells for $8.32. write the equations for the total cost, c, and the revenue, r, then use the graphing method to determine how many balls must be sold to break even.
Answers: 3
question
Mathematics, 21.06.2019 20:10
Over which interval is the graph of f(x) = x2 + 5x + 6 increasing?
Answers: 1
question
Mathematics, 21.06.2019 20:40
Ineed someone to me answer my question i have to have this done and knocked out
Answers: 2
question
Mathematics, 21.06.2019 21:30
The price of a visit to the dentist is calculated according to the formula 50+100n50+100n where nn is the number of cavities the dentist finds. on your last visit to the dentist, 22 cavities were found. what was the cost of your visit?
Answers: 2
You know the right answer?
In 18 days, 20 workers can build a school. how many days would it take if there were only 12 workers...
Questions
question
Mathematics, 18.03.2021 01:40
question
Mathematics, 18.03.2021 01:40
question
Mathematics, 18.03.2021 01:40
question
Mathematics, 18.03.2021 01:40
question
Mathematics, 18.03.2021 01:40
question
Mathematics, 18.03.2021 01:40
Questions on the website: 13722363