Mathematics, 26.09.2019 18:00 miguel20000000

M5_a3. the expected project completion time for the construction of a pressure vessel is 18 monthsand the project variance is 7. (note: when using the z tables – round your z values to two decimal placesbefore getting the probabilities from the tables. do not round standard deviations prior to calculating zvalues)note: enter probabilities as decimals (i. e 92.31% should be entered as 0.9231)a) what is the probability that the project will require at least 19 months? (enter 4 decimal placesfrom distribution tables)b) what is the probability that the project will be completed within 24 months? (enter 4 decimalplaces from distribution tables)c) what is the probability that the project will require at least 21 months? (enter 4 decimal placesfrom distribution tables)d) what is the probability that the project will be completed within 15 months? (enter 4 decimalplaces from distribution tables)e) what is the probability that the project will take between 16 and 24 months to complete? (enter4 decimal places from distribution tablesshow work

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:40
Carrie started with 12 ounces of water when she begin to walk. when she was finish walking she had 2 1/4 ounces of water left. how much did she drank
Answers: 2
question
Mathematics, 21.06.2019 17:00
The general form of the quetion of a circle is ax^2+by^2+cx+dy+e=0 where a=b=0 if the circle has a radius of three units and the center lies on the y axis which set of values of a, b, c, d, and e might correspond to the circle
Answers: 1
question
Mathematics, 21.06.2019 17:40
Given abcd ac=38 and ae=3x+4 find the value of x
Answers: 2
question
Mathematics, 21.06.2019 18:00
Assume that the weights of quarters are normally distributed with a mean of 5.67 g and a standard deviation 0.070 g. a vending machine will only accept coins weighing between 5.48 g and 5.82 g. what percentage of legal quarters will be rejected? round your answer to two decimal places.
Answers: 1
You know the right answer?
M5_a3. the expected project completion time for the construction of a pressure vessel is 18 monthsan...