8) the cost, c, in dollars, of operating a concrete-cutting machine is modelled by
c = 2.2n? - 66n+ 655, where n is the number of minutes the machine is run. how long must the
machine run for the operating cost to be at a minimum? what is the minimum cost?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:50
For the equations below which statement is true ?
Answers: 2
question
Mathematics, 21.06.2019 17:30
10 ! in a race, nick is 50 feet in front of jay after ten seconds. how fast can nick run, if jay can run 20 feet per second?
Answers: 1
question
Mathematics, 21.06.2019 22:10
Aculture started with 2,000 bacteria. after 8 hours, it grew to 2,400 bacteria. predict how many bacteria will be present after 19 hours . round your answer to the nearest whole number. p=ae^kt
Answers: 1
question
Mathematics, 21.06.2019 23:30
Hundred and tens tables to make 430 in five different ways
Answers: 1
You know the right answer?
8) the cost, c, in dollars, of operating a concrete-cutting machine is modelled by
c = 2.2n?...
Questions
question
History, 11.03.2021 23:00
Questions on the website: 13722361