You work as a coordinator for data entry projects. on one project, the status report shows that 15% of the work was completed in 6 days. if the work progresses at the same rate, how many more days will be required to complete the remaineder of the projects?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Find the distance between (0,5) & (-4,2)
Answers: 1
question
Mathematics, 21.06.2019 20:30
What is 140% of 25? because i need
Answers: 2
question
Mathematics, 21.06.2019 22:30
Will mark brainlist what is the slope of the line passing through the points (-2, -8) and (-3,-9)? -7/5-5/71-1
Answers: 2
question
Mathematics, 22.06.2019 02:00
There are a total of 75 students in the robotics club and science club. the science club has 9 more students than the robotics club. how many students are in the science club?
Answers: 1
You know the right answer?
You work as a coordinator for data entry projects. on one project, the status report shows that 15%...
Questions
question
English, 15.12.2020 04:00
question
Mathematics, 15.12.2020 04:00
Questions on the website: 13722367