Mathematics, 12.02.2020 18:56 Yaoicx681

Five workstations (1, 2, 3, 4, and 5) that produce about ten similar parts must be arranged into an in-line layout. The daily flow of parts between workstations is as follows: 40 parts from stations 5 to 2, 35 parts from stations 5 to 3, 20 parts from stations 3 to 1, 25 parts from stations 1 to 4, 60 parts from 3 to 2, 15 parts from stations 2 to 5, and 30 parts from stations 4 to 2.

A) Use the Hollier algorithm described to determine the most logical sequence of stations in the work system.
B) Draw the network diagram for the system.
C) Compute the percentage of in-sequence moves, by-passing moves, and backflow moves for the sequence.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Julia is going for a walk through the neighborhood. what unit of measure is most appropriate to describe the distance she walks?
Answers: 1
question
Mathematics, 21.06.2019 18:30
The height of a flare fired from the deck of a ship in distress can be modeled by h(t)= -2(8t^2-52t-28), where h is the height of the flare above water and t is the time in seconds. a. find the time it takes the flare to hit the water.
Answers: 1
question
Mathematics, 21.06.2019 18:30
If you are trying to move an attached term across the equal sign (=), what operation would you use to move it?
Answers: 2
question
Mathematics, 21.06.2019 18:50
Need 50 will mark brainliest answer. find the lengths of all the sides and the measures of the angles.
Answers: 1
You know the right answer?
Five workstations (1, 2, 3, 4, and 5) that produce about ten similar parts must be arranged into an...
Questions
question
English, 07.12.2020 21:40
Questions on the website: 13722363