Given that 224 hours of work need to be done to complete a project.
{i) How long will it take 4 men, each working an 8-hour day to complete the project?
(ii) If each of them is paid $7-50 per hour, how much will it cost to employ them altogether
(iii) How many hours of overtime must they put in per day if the project is to be completed in 4 days?
(iv) Given that the overtime rate of payment is 1- times as much as the regular hourly rate, find the cost
of the project now.

3. If 8 horses can finish eating the grass of a field in 12 days, in how many days will 6 horses finish eating it?

4. 10 cooks working for 8 hours each, can prepare a meal for 536 people. How many cooks will be needed to prepare a meal for 737 people if they are required to prepare the meal in 5 hours?

5. 100 people have food for 20 days at the rate 2kg per person per day. If 20 people left, how long will the food last of they eat

(a) 2kg per person daily?

(b) 1.8 kg per person daily?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
0if x and y vary inversely and y=6 as x=7, what is the constant of variation?
Answers: 1
question
Mathematics, 21.06.2019 21:00
Ade and abc are similar. which best explains why the slope of the line between points a and d is the same as the slope between points a and b?
Answers: 2
question
Mathematics, 21.06.2019 21:00
Me! i will mark you brainliest if you are right and show your i don't get polynomials and all the other stuff. multiply and simplify.2x(^2)y(^3)z(^2) · 4xy(^4)x(^2)show your
Answers: 2
question
Mathematics, 21.06.2019 22:30
Will mark determine whether the conjecture is true or false. give a counterexample for any false conjecture. given: points r, s, and t conjecture: r, s, and t are coplanar. a) false; the points do not have to be in a straight line. b) true c) false; the points to not have to form right angles. d) false; one point may not be between the other two.
Answers: 1
You know the right answer?
2.
Given that 224 hours of work need to be done to complete a project.
{i) How long will i...
Questions
Questions on the website: 13722367