Mathematics, 19.02.2020 04:55 yangyang7

A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 108 and 120?A) 0.0227B) 0.1058C) minus−2.00D) 0.9773E) 0.4773

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Need now max recorded the heights of 500 male humans. he found that the heights were normally distributed around a mean of 177 centimeters. which statements about max’s data must be true? a) the median of max’s data is 250 b) more than half of the data points max recorded were 177 centimeters. c) a data point chosen at random is as likely to be above the mean as it is to be below the mean. d) every height within three standard deviations of the mean is equally likely to be chosen if a data point is selected at random.
Answers: 1
question
Mathematics, 21.06.2019 20:00
Simplify 24÷(-2)(3)+7 a. -29 b. 3 c. 11
Answers: 1
question
Mathematics, 21.06.2019 23:30
For the feasibility region shown below find the maximum value of the function p=3x+2y
Answers: 3
question
Mathematics, 22.06.2019 02:00
Light travels at 186,000 miles per second. light takes about 1 1? 3 seconds to travel from the earth to the moon. calculate the distance between the earth and the moon based on the speed of light.
Answers: 2
You know the right answer?
A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the c...
Questions
question
Mathematics, 10.02.2021 05:50
question
Social Studies, 10.02.2021 05:50
question
Mathematics, 10.02.2021 05:50
question
Social Studies, 10.02.2021 05:50
question
Mathematics, 10.02.2021 05:50
question
Mathematics, 10.02.2021 05:50
Questions on the website: 13722367