subject
Mathematics, 21.02.2020 02:11 mannster03

Suppose a particular project has an expected completion time of 30 days; in other words, the critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this information, please answer the following questions:

Find the probability that the project:
(1) Would be completed within 40 days
(2) Would take longer than 40 days to finish
(3) Would be completed within 20 days
(4) Would take longer than 20 days to finish

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
∠1 and ∠2 are complementary. ∠1=x°∠2=(3x+30)° select from the drop down menu to correctly answer the question. what is the value of x? . a.15 b.25 c.30 d.40 e.55
Answers: 1
question
Mathematics, 21.06.2019 17:30
What is the least common factor of 6 and 8
Answers: 2
question
Mathematics, 21.06.2019 18:00
Li buys supplies so he can make and sell key chains. he begins to make a profit only after he sells 4 key chains. what point on the graph makes the most sense in this situation?
Answers: 2
question
Mathematics, 21.06.2019 19:10
Which ordered pair is a solution of the equation? y + 5 = 2(2+1) choose 1 answer ® only (5,10 ® only (-1,-5) © both (5, 10) and (-1,-5) 0 neither
Answers: 1
You know the right answer?
Suppose a particular project has an expected completion time of 30 days; in other words, the critica...
Questions
question
Mathematics, 05.05.2020 01:25
question
Social Studies, 05.05.2020 01:25
question
Mathematics, 05.05.2020 01:25
Questions on the website: 13722360