To complete a task in 16 days a company needs
5 people each working in 6 hours per day
The company decides to have
8 people each working in 4 hours per day
Assuming that each person works at the same rate, how many days will the task take to complete
Answers: 2
Mathematics, 21.06.2019 13:30
Evaluate 4 a for a = 5 2/3 . express your answer in simplest form.
Answers: 1
Mathematics, 21.06.2019 18:30
According to the 2008 u.s. census, california had a population of approximately 4 × 10^7 people and florida had a population of approximately 2 × 10^7 people. which of the following is true? a. the population of florida was approximately two times the population of california. b. the population of florida was approximately twenty times the population of california. c. the population of california was approximately twenty times the population of florida. d. the population of california was approximately two times the population of florida.
Answers: 1
Mathematics, 21.06.2019 19:30
Ann and betty together have $60 ann has $9 more than twice betty’s amount how much money dose each have
Answers: 1
To complete a task in 16 days a company needs
5 people each working in 6 hours per day
...
5 people each working in 6 hours per day
...
Mathematics, 25.03.2020 12:42
Geography, 25.03.2020 12:42
Biology, 25.03.2020 12:44
Mathematics, 25.03.2020 12:46
Biology, 25.03.2020 12:46
Mathematics, 25.03.2020 12:48
Social Studies, 25.03.2020 12:50
Mathematics, 25.03.2020 12:54
English, 25.03.2020 12:54
Computers and Technology, 25.03.2020 12:55
Mathematics, 25.03.2020 12:55
Computers and Technology, 25.03.2020 12:56
Mathematics, 25.03.2020 12:57
Mathematics, 25.03.2020 12:57