An auto service center that specializes in oil changes has two service bays that serve, on average, a total of 24 cars per eight-hour business day. On average, each bay can finish one oil change in 30 minutes.

What is the design capacity? 30 min per oil change per bay (8 hr day x 2 (30 min each) =16 x 2 bays =?)

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
Myron put $5000 in a 2-year cd playing 3% interest, compounded monthly. after 2 years, he withrew all his money. what was the amount of the withdrawal?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Is the power produced directly proportional to the wind speed, give reasons for your answer?
Answers: 1
question
Mathematics, 21.06.2019 22:30
The area of the map is the product of the length and width. write and expression for the area as the product of the two binomials do not multiply
Answers: 2
question
Mathematics, 22.06.2019 02:30
Factor this polynomial completely. 12x^2+ x-6
Answers: 1
You know the right answer?
An auto service center that specializes in oil changes has two service bays that serve, on average,...
Questions
question
Mathematics, 26.07.2019 05:30
Questions on the website: 13722363