subject
Mathematics, 26.02.2020 22:30 dwebster9099

PERT analysis computes the variance of the total project completion time as A. the sum of the variances of all activities not on the critical path. B. the variance of the final activity of the project. C. the sum of the variances of all activities on the critical path. D. the sum of the variances of all activities in the project.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:50
If your teacher tells you to do questions 6 through 19 in your math book for homework, how many questions is that
Answers: 1
question
Mathematics, 21.06.2019 19:50
Raj encoded a secret phrase using matrix multiplication. using a = 1, b = 2, c = 3, and so on, he multiplied the clear text code for each letter by the matrix to get a matrix that represents the encoded text. the matrix representing the encoded text is . what is the secret phrase? determine the location of spaces after you decode the text. yummy is the corn the tomato is red the corn is yummy red is the tomato
Answers: 2
question
Mathematics, 22.06.2019 00:00
Astocks price gained 3% in april and 5% in may and then lost 4% in june and 1% in july during which month did the stocks price change the most
Answers: 1
question
Mathematics, 22.06.2019 01:40
The graph below shows the line of best fit for data collected on the number of cell phones in cell phone cases sold at the local electronic store on four different days
Answers: 3
You know the right answer?
PERT analysis computes the variance of the total project completion time as A. the sum of the varian...
Questions
question
Mathematics, 22.09.2019 18:30
question
Mathematics, 22.09.2019 18:30
Questions on the website: 13722363