Travis can lay a slab of concrete in 20 hours while devante can do it in 12 hours. IF travis and devante work together how long will it take them

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
What is a graph with a never ending line called?
Answers: 1
question
Mathematics, 21.06.2019 18:30
The base of a triangle exceeds the height by 9 inches. if the area is 180 square inches, find the length of the base and the height of the triangle.
Answers: 1
question
Mathematics, 21.06.2019 23:00
12 out of 30 people chose their favourite colour as blue caculate the angle you would use for blue on a pie chart
Answers: 1
question
Mathematics, 21.06.2019 23:40
Which set of side lengths form a right side? a) 3ft,6ft,5ft b)50 in,48in,14in c)53m,48m,24m d)8cm,17cm,14cm
Answers: 2
You know the right answer?
Travis can lay a slab of concrete in 20 hours while devante can do it in 12 hours. IF travis and dev...
Questions
question
Mathematics, 17.10.2020 14:01
question
English, 17.10.2020 14:01
Questions on the website: 13722361