An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

a) What are the minimum and maximum cycle times?
b) What range of output is theoretically possible for the line?
c) What is the minimum number of worksheets needed if the maximum output rate is to be sought?
d) What cycle time will provide an output rate of 125 units per day?
e) What output potential will result if the cycle time is (1) 9 minutes? and (2) 15 minutes?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
What is the perimeter of a rectangular building that is 80 feet wide and 140 feet deep?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Fa bus driver leaves her first stop by 7: 00 a.m., her route will take less than 37 minutes. if she leaves after 7: 00 a.m., she estimates that the same route will take no less than 42 minutes. which inequality represents the time it takes to drive the route, r?
Answers: 3
question
Mathematics, 22.06.2019 01:00
The answer is 7.2 how would you put this as money
Answers: 2
question
Mathematics, 22.06.2019 01:20
Find the axis of symmerty for x y=x squared -4x-8
Answers: 1
You know the right answer?
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total tim...
Questions
question
English, 13.11.2020 07:40
question
Mathematics, 13.11.2020 07:40
Questions on the website: 13722367