Mathematics, 10.03.2020 00:24 Emiann222

Two companies working together can clear a parcel of land in 24 hours. Working alone, it would take Company A 10 hours longer to clear the land than it would Company B. How long would it take Company B to clear the parcel of land alone

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 22:30
Atotal of 766 tickets were sold for the school play. they were either adult tickets or student tickets. there were 66 more student tickets sold than adult tickets. how many adult tickets were sold?
Answers: 1
question
Mathematics, 21.06.2019 22:30
Solve: 25 points find the fifth term of an increasing geometric progression if the first term is equal to 7−3 √5 and each term (starting with the second) is equal to the difference of the term following it and the term preceding it.
Answers: 1
question
Mathematics, 22.06.2019 01:30
If 5x - 2 = -12, then x = a) -50 b) -4.4 c) -2.8 d) -2
Answers: 1
question
Mathematics, 22.06.2019 02:30
Six random samples were taken each year for three years. the table shows the inferred population for each type of fish for each year.
Answers: 1
You know the right answer?
Two companies working together can clear a parcel of land in 24 hours. Working alone, it would take...