A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
12. decide whether each statement is always true, sometimes true, or never true. a. when corresponding points of an original figure and its reflection are connected, the resulting segments are all perpendicular to the line of reflection. b. when a point is reflected over a horizontal line, the y-coordinate of the point stays the same. answer both questions and explain
Answers: 2
question
Mathematics, 21.06.2019 14:40
3× __ -2=15 7 2× __+1=7 5 7× =22 15 5× __+10=2 8 × __+4=20 6 × =10 3 × __+2=8 6 × __+8=8 9 × __+7=20 6
Answers: 3
question
Mathematics, 21.06.2019 15:30
Afurniture store has 1,500 chairs in storage. a manager uses three delivery receipts to simulate samples to check 100 chairs and note the number of brown chairs. suppose the actual number of brown chairs is 1,080. about how many brown chairs are
Answers: 1
question
Mathematics, 21.06.2019 17:00
Issof claims that the scale factor is 1/2. which statement about his claim is correct
Answers: 3
You know the right answer?
A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance...