Suppose a process has an upper specification limit 5.60, and a lower specification limit 5.0. If a customer requires a demonstrated Cp of 2.0. What must the process standard deviation be?

a) 0.1
b) 0.05
c)0.15

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Based on the figures as marked, /\rqs = —
Answers: 1
question
Mathematics, 21.06.2019 17:30
Consider the graph of the exponential function y=3(2)×
Answers: 1
question
Mathematics, 21.06.2019 18:00
The given dot plot represents the average daily temperatures, in degrees fahrenheit, recorded in a town during the first 15 days of september. if the dot plot is converted to a box plot, the first quartile would be drawn at __ , and the third quartile would be drawn at __ link to graph: .
Answers: 1
question
Mathematics, 21.06.2019 22:30
What is the name of a polygon that has four congruent sides and theses angle measures 60,120,60,120?
Answers: 1
You know the right answer?
Suppose a process has an upper specification limit 5.60, and a lower specification limit 5.0. If a c...
Questions
question
Mathematics, 06.12.2019 04:31
question
Mathematics, 06.12.2019 04:31
question
Mathematics, 06.12.2019 04:31
Questions on the website: 13722361