Mathematics, 07.04.2020 04:12 grantjaylynn

A project has an expected duration of 34 weeks with a critical path variance of 6.
1) Suppose the project network is given and the critical path is identified on the network.
2) Suppose the normal time, crash time, and the associated cost for each activity is given.
You have been asked by your supervisor to prepare a research paper that addresses the follow criteria:
a) What is the probability that the project will be completed in 32 weeks or less?
b) If the project is to be shortened by four days, list the process you would take to determine which activities, in order of reduction, would be shortened and the resulting cost.
c) Describe project cost and the requirements for its determination and application ina production facility.
d) Analyze the implications of changes in the parameters of project timing and cost determination.
e) Evaluate the application of project cost and timing concepts on a firm's business operations. What is the probability that the project will be completed in 32 weeks or less?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:20
Read the equations in the table below. then drag a description of the situation and a table to represent each equation. indicate whether each of the relationships is proportional or non-proportional.
Answers: 1
question
Mathematics, 21.06.2019 18:00
Enter numbers to write 0.000328 0.000328 in scientific notation. 1 1 0.000328=3.28 × 0 . 000328 = 3 . 28 × =3.28×10 = 3 . 28 × 10
Answers: 1
question
Mathematics, 21.06.2019 21:30
He ! a group of farmers planned to clean 80 acres of wheat per day to finish the work on schedule. right before the work started, they received a new piece of machinery that them clean 10 more acres per day than originally planned. as a result of increased productivity in the last day before the deadline they only had to clean 30 acres. how many acres of wheat did the group of farmers have to clean?
Answers: 1
question
Mathematics, 21.06.2019 21:30
Acoffee shop orders at most $3,500 worth of coffee and tea. the shop needs to make a profit of at least $1,900 on the order. the possible combinations of coffee and tea for this order are given by this system of inequalities, where c = pounds of coffee and t = pounds of tea: 6c + 13t ≤ 3,500 3.50c + 4t ≥ 1,900 which graph's shaded region represents the possible combinations of coffee and tea for this order?
Answers: 1
You know the right answer?
A project has an expected duration of 34 weeks with a critical path variance of 6.
1) Suppose...
Questions
question
History, 02.10.2020 15:01
Questions on the website: 13722360