24 workers can complete a new home construction
in 14 days. How many workers will be required to
complete this tasks in 21 days?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:10
Which graph represents the function g(x) = |x + 4| + 2?
Answers: 1
question
Mathematics, 21.06.2019 20:00
Ialready asked this but i never got an answer. will give a high rating and perhaps brainliest. choose the linear inequality that describes the graph. the gray area represents the shaded region. y ≤ –4x – 2 y > –4x – 2 y ≥ –4x – 2 y < 4x – 2
Answers: 1
question
Mathematics, 21.06.2019 21:00
Construct the graph that models the given situation
Answers: 1
question
Mathematics, 22.06.2019 03:00
What is the slope-intercept form for each equation in this system? compare the slopes and y-intercepts to describe the graph of the system. 3x - 4y = 28 4x + 10y = 20
Answers: 1
You know the right answer?
24 workers can complete a new home construction
in 14 days. How many workers will be required...
Questions
question
Biology, 03.06.2021 17:50
question
Computers and Technology, 03.06.2021 17:50
Questions on the website: 13722363