An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?

A) About 8 days

B) About 9 days

C) About 10 days

D) About 11 days

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Y=(x+3)(x-4)(x+1)^2 sulutions? multiplicity?
Answers: 1
question
Mathematics, 21.06.2019 21:00
Choose the equation below that represents the line that passes through the point (2, 4) and has a slope of 3. a) y − 4 = 3(x − 2) b) y − 2 = 3(x − 4) c) y + 4 = 3(x + 2) d) y + 2 = 3(x + 4)
Answers: 1
question
Mathematics, 21.06.2019 22:10
What is the circumference of a circle with an area of 50.24 cm²?
Answers: 2
question
Mathematics, 21.06.2019 23:30
Scenario: a rectangular plot of ground is 5 meters longer than it is wide. its area is 20,000 square meters. question: what equation will you find the dimensions? note: let w represent the width. options: w(w+5)=20,000 w^2=20,000+5 (w(w+5))/2=20,000 w+2(w+5)=20,000
Answers: 1
You know the right answer?
An activity has a pessimistic time that is four times as long as its most likely time and six times...
Questions
question
Mathematics, 21.08.2019 10:10
question
Mathematics, 21.08.2019 10:10
question
Physics, 21.08.2019 10:10
question
Social Studies, 21.08.2019 10:10
Questions on the website: 13722367