Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's earliest finish is 18: while C's is 20. F's late start is 26. Which of the following is definitely true? a. D is critical and has zero slack.
b. B is a critical activity.
c. F is critical and has zero slack.
d. D has no slack but is not critical.
e. C is completed before B.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
What are potential hypotheses (explanations) regarding why there are ecological equivalents between many metatherians and eutherians? discuss your hypothesis in terms of the processes that could lead to the current ecologies and distributions of metatherians and eutherians.
Answers: 2
question
Mathematics, 21.06.2019 21:30
At the county fair, the baxter family bought 6 hot dogs and 4 juice drinks for $12.90. the farley family bought 3 hot dogs and 4 juice drinks for $8.55. find the price of a hot dog and the price of a juice drink.
Answers: 1
question
Mathematics, 21.06.2019 22:00
If my mom gets $13.05 an hour, and she works from 3: 30 to 10: 45 in the morning, how much money does my mom make?
Answers: 1
question
Mathematics, 22.06.2019 01:00
Sanderson is having trouble with his assignment. his shown work is as follows: − 3 7 7 3 = − 3 7 × 7 3 = − 21 21 = −1 however, his answer does not match the answer that his teacher gives him. complete the description of sanderson's mistake. find the correct answer.
Answers: 3
You know the right answer?
Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's ear...
Questions
question
Chemistry, 18.11.2020 07:20
Questions on the website: 13722361