To complete a task a company needs 5 people each working for 6 hours pr day. The company decides to have 8 people working for 4 hours per day. Assuming that each person works the same rate, how many days will the task take to complete?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
43lbs of tomatos cost $387. how much would 41lbs cost
Answers: 1
question
Mathematics, 21.06.2019 19:30
In the geometric progression –3, 12, −48… what term is 3,072?
Answers: 2
question
Mathematics, 21.06.2019 20:00
Anyone? 15m is what percent of 60m; 3m; 30m; 1.5 km?
Answers: 1
question
Mathematics, 21.06.2019 20:30
Find the value of x. give reasons to justify your solutions! c ∈ ae
Answers: 1
You know the right answer?
To complete a task a company needs 5 people each working for 6 hours pr day. The company decides to...
Questions
question
Mathematics, 12.09.2019 23:10
question
Health, 12.09.2019 23:10
Questions on the website: 13722360