Mathematics, 07.07.2020 02:01 andybiersack154

A and b can do a piece of work in 30 days while b and c can do the same work in 24 days and c and a in 20 days. If they all work together, in how many days will the work finish?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Isee the amount was $90.00 then reduced to $75.00 , what is the percent ?
Answers: 1
question
Mathematics, 21.06.2019 18:00
You spin the spinner shown below once. each sector shown has an equal area. what is p(beaver ) p(beaver)? if necessary, round your answer to 2 2 decimal places.
Answers: 2
question
Mathematics, 21.06.2019 20:00
Given the equation y − 4 = three fourths(x + 8) in point-slope form, identify the equation of the same line in standard form. −three fourthsx + y = 10 3x − 4y = −40 y = three fourthsx + 12 y = three fourthsx + 10
Answers: 1
question
Mathematics, 21.06.2019 23:00
Which geometric principle is used to justify the construction below?
Answers: 1
You know the right answer?
A and b can do a piece of work in 30 days while b and c can do the same work in 24 days and c and a...