35 workers are employed to complete the construction in 16 days. Before the work starts, he is told to complete the task in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
When only separate discreet points are graphed it is called?
Answers: 1
question
Mathematics, 21.06.2019 17:30
Any is very appreciated! (picture is provided below)not sure how to do this at all won't lie
Answers: 1
question
Mathematics, 21.06.2019 19:10
Girardo is using the model below to solve the equation . girardo uses the following steps: step 1 add 4 negative x-tiles to both sides step 2 add 1 negative unit tile to both sides step 3 the solution is which step could be adjusted so that gerardo's final step results in a positive x-value? in step 1, he should have added 4 positive x-tiles to both sides. in step 1, he should have added 3 negative x-tiles to both sides. in step 2, he should have added 4 negative unit tiles to both sides. in step 2, he should have added 1 positive unit tile to both sides.
Answers: 2
question
Mathematics, 21.06.2019 22:00
Uestion 1(multiple choice worth 5 points) (05.02)alex wants to paint one side of his skateboard ramp with glow-in-the-dark paint, but he needs to know how much area he is painting. calculate the area of the isosceles trapezoid. isosceles trapezoid with top base 12 feet, bottom base of 18 feet, and height of 6 feet. 72 ft2 84 ft2 90 ft2 108 ft2
Answers: 1
You know the right answer?
35 workers are employed to complete the construction in 16 days. Before the work starts, he is told...
Questions
question
Mathematics, 19.09.2019 07:30
Questions on the website: 13722362