Mathematics, 16.08.2020 01:01 Roselyn0131

There is a job that needs to be done. Bob can complete the job in 10 days alone, Jeff can complete the job in 15 days alone. Bob and Jeff work together for 4 days. Then Jeff has to finish the rest. How many more days does Jeff need?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Use the knowledge of x- and y- intercepts to choose the correct graph of the equation 3x+6y=6
Answers: 1
question
Mathematics, 21.06.2019 17:00
Acylinder and its dimensions are shown. which equation can be used to find v, the volume of the cylinder in cubic centimeters?
Answers: 1
question
Mathematics, 21.06.2019 17:40
Which basic geometric term has no width, no length, and no thickness? line b. point c. angle d. plane
Answers: 2
question
Mathematics, 21.06.2019 19:00
The weekly revenue for a company is r = 3p^2 + 60p + 1060, where p is the price of the company's product. what price will result in a revenue of $1200.
Answers: 1
You know the right answer?
There is a job that needs to be done. Bob can complete the job in 10 days alone, Jeff can complete t...