5. 35 workers are employed to complete a construction
project in 16 days. Before the p...
Mathematics, 28.08.2020 14:01 calmicaela12s
E LEVEL
5. 35 workers are employed to complete a construction
project in 16 days. Before the project starts, the boss
of the company is told that he needs to complete
the project in 14 days. Assuming that all the workers
work at the same rate, how many more workers does
he need to employ in order to complete the project
on time?
P. S: I need this answer with Proportion (Direct/Inverse) method
Answers: 1
Mathematics, 21.06.2019 21:30
Money off coupons have been circulated to 300 households. only 2/5 of these were redeemed (used) in the local supermarket to get a free shampoo. what fraction of coupons were unused? (ps: write how you got the answer)
Answers: 1
Mathematics, 21.06.2019 22:00
The customer price index(cpi), which measures the cost of a typical package of customer goods,was 208.8 in 2011 and 244.1 in 2016.let x=11 corresponding to the year 2011 an estimate to cpi into 2013 and 2014. assume that the data can be modeled by a straight line and the trend to continue idenfinitely.use data points to find such a line and then estimate the requested quantities
Answers: 1
Mathematics, 21.06.2019 22:10
Aadc is formed by reflecting aabc across line segment ac, as shown in the figure. if the length of ac is 4 units, the area of aadc is square units.
Answers: 3
Physics, 25.12.2021 03:50
Mathematics, 25.12.2021 03:50
Computers and Technology, 25.12.2021 03:50
English, 25.12.2021 03:50
Social Studies, 25.12.2021 03:50