Mathematics, 30.08.2020 14:01 isabellemaine

A, B and C together can finish a piece of work in 4 days, A alone can do it in 12 days and B alone in 18 days. How many days will be taken by C to do it alone?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 22:30
Which of the following represents the length of a diagonal of this trapezoid?
Answers: 1
question
Mathematics, 21.06.2019 22:50
What is the ordered pair of m’ after point m (5, 6) is rotated 90° counterclockwise?
Answers: 2
question
Mathematics, 22.06.2019 00:00
Add, subtract, multiply, or divide as indicated. list any restrictions for the variable(s) and simplify the answers when possible. 1) x-2 / x+5 + 3x / 2x-1 2) x+6 / x-6 - x^2 / x+6 3) x+9 / x-4 + x+2 / x^2-11x+28 4) x / x^2-64 + 11 / 2x^2+11x-40 5) 5 / x + 11 / x-3 - x-4 / x^2+2x-15
Answers: 1
question
Mathematics, 22.06.2019 00:50
Assume that adults have iq scores that are normally distributed with a mean of mu equals 100 and a standard deviation sigma equals 20. find the probability that a randomly selected adult has an iq between 80 and 120.assume that adults have iq scores that are normally distributed with a mean of mu equals 100 and a standard deviation sigma equals 20. find the probability that a randomly selected adult has an iq between 80 and 120.
Answers: 3
You know the right answer?
A, B and C together can finish a piece of work in 4 days, A alone can do it in 12 days and B alone i...