It takes 2 finish carpenters 8 days to do the work. Each finish carpenter earns $37.50 per hour and works 7 hours per day. How much will it
cost to hire the finish carpenters?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:20
Find the slope of a line given the following two points
Answers: 1
question
Mathematics, 21.06.2019 19:30
Im literally having a mental breakdown
Answers: 1
question
Mathematics, 21.06.2019 19:40
Which is greater, 7 p 5 or 7 c 5? 7p5 7c5
Answers: 1
question
Mathematics, 21.06.2019 20:00
Choose the linear inequality that describes the graph. the gray area represents the shaded region. a: y ≤ –4x – 2 b: y > –4x – 2 c: y ≥ –4x – 2 d: y < 4x – 2
Answers: 2
You know the right answer?
It takes 2 finish carpenters 8 days to do the work. Each finish carpenter earns $37.50 per hour and...
Questions
question
Mathematics, 18.10.2020 06:01
question
Mathematics, 18.10.2020 06:01
question
Mathematics, 18.10.2020 06:01
question
Biology, 18.10.2020 06:01
question
Mathematics, 18.10.2020 06:01
question
Social Studies, 18.10.2020 06:01
Questions on the website: 13722359