Mathematics, 09.09.2020 16:01 tiffanybrown703

There is a machine shop with only one machine. Arrival rate to the shop is 10 parts per hour on average. The average machining time is 5 minutes per part. The machine shop is considering replacing the old machine with a new high speed machine, which is expected to reduce machining time by 20% (4 minutes per part). Also, the shop is expecting attracting 20% more customers (12 parts per hour), with the new machine. Compare the expected time in the shop for each part with the old and with the new machine. How much % can we reduce the time in the shop by introducing the new machine?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:30
∠1 and ∠2 are complementary. ∠1=x°∠2=(3x+30)° select from the drop down menu to correctly answer the question. what is the value of x? . a.15 b.25 c.30 d.40 e.55
Answers: 1
question
Mathematics, 21.06.2019 15:10
Two lines that do not intersect are skew. always sometimes or never
Answers: 1
question
Mathematics, 21.06.2019 18:30
Can someone me do math because i am having a breakdown rn because i don’t get it
Answers: 1
question
Mathematics, 21.06.2019 18:30
True or false? a circle could be circumscribed about the quadrilateral below.
Answers: 3
You know the right answer?
There is a machine shop with only one machine. Arrival rate to the shop is 10 parts per hour on aver...
Questions
question
Mathematics, 24.01.2020 07:31
question
Mathematics, 24.01.2020 07:31
question
Mathematics, 24.01.2020 07:31
Questions on the website: 13722362