Between 15,000 yd and 16,000 yd of earth must be trucked away from a construction site. The trucks can remove 1000 yd per day, and 10,500 yd has
already been removed. How many days are needed?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Aiden drives to school and back each day. the school is 16 miles from his home. he averages 40 miles per hour on his way to school. if his trip takes 1 hour, at approximately what speed does aiden drive home?
Answers: 1
question
Mathematics, 21.06.2019 20:00
You have 138.72 in your saving account u take out 45.23 and 18.00 you deposit 75.85 into your account
Answers: 1
question
Mathematics, 21.06.2019 23:30
Robin spent 25% more time on his research project than he had planned he’s been an extra h ours on the project which of the following expressions could represent the number of hours rob actually spent on the project
Answers: 3
question
Mathematics, 22.06.2019 02:30
Robert has 78 tomato lants and 56 cucumber plants .he wants to plant them in rows that only have one type of plant in each row with the same number of plants in each row. how many plants should he put in each row and how many rows of each type of plant will he need
Answers: 1
You know the right answer?
Between 15,000 yd and 16,000 yd of earth must be trucked away from a construction site. The trucks...
Questions
question
Health, 06.05.2021 01:00
question
Mathematics, 06.05.2021 01:00
question
Mathematics, 06.05.2021 01:00
question
Mathematics, 06.05.2021 01:00
question
Mathematics, 06.05.2021 01:00
Questions on the website: 13722360